Posted: Wed Apr 19, 2006 9:37 am Post subject: The Boss
I am trying to implement a basic change management process at a company. CAB is comprised of 4 IT managers and requires approval by all for before a change is approved.
The director ( who is one of the four) wants to have final approval on all changes and want the ability to push a change through.
Joined: Feb 28, 2006 Posts: 411 Location: Coventry, England
Posted: Wed Apr 19, 2006 5:33 pm Post subject:
Ken
This sounds very much like our paper system, but we have 6 signatories based on roles not positions in the company
I think best practice is that you resist (if possible) as your Change manager (probably answerable to said director) should have final say after taking into account the Business requirements - In practice will your director have the time to sign of all the changes? - ours are far too busy.
It will probably be ok in the beginning with only a few changes per month, but as the process is used by more people, we have found that they were unavailable and we needed to find deputies more and more.
As I said we now have sign-off based on roles (we are a Managed Services provider)
Implementer, Customer Service manager for Client, Service Desk, Operations, Peer(for Technical content) and Change Team