Introducing a new change freeze process?

Discuss and debate ITIL Change Management issues
Post Reply
User avatar
Turtietoo
Newbie
Newbie
Posts: 1
Joined: Tue Oct 04, 2016 8:00 pm

Wed Oct 05, 2016 6:12 am

I'm starting a new CM role and processes maturity seems to be a key thing for me to look at. They will be having a change freeze & period of enhanced change control either side of it. Any experience of introducing a robust process appreciated!
I'm thinking: identify key business & IT stakeholders. Comm to them about these periods & that they will be required to review any submitted RFCs for approval during. Initiators to identify any known RFCs needed during that period & have them raised 1 week before? Rest would be rejected unless business need, risk minimal, due diligence etc documented in the RFC. Then they would go to an e-CAB for approval by identified stakeholders?


User avatar
UKVIKING
ITIL Expert
ITIL Expert
Posts: 3639
Joined: Fri Sep 15, 2006 8:00 pm
Location: London, UK

Wed Oct 05, 2016 5:21 pm

A Change Freeze usually means no Changes except under extremely rigorous conditions

You as the new CM needs to define this first

And then distribute to all stakeholders and change raisers to concur

And then once agreed manage it like it is the reason for being

Only those that meet the conditions get processed

Report to mgmt.
Report to stakeholder

Vulgar: This is where CM separates the sheep from the goats and the wolf.

You are the wolf. You have senior mgmt to override you in accordance with defined process above otherwise.. you become a goat or sheep and are useless as a CM - no authority just a ticket punch checker
John Hardesty
ITSM Manager's Certificate (Red Badge)

Change Management is POWER & CONTROL. /....evil laughter
User avatar
module
Newbie
Newbie
Posts: 1
Joined: Wed Oct 05, 2016 8:00 pm

Thu Oct 06, 2016 10:06 am

Hi..am looking for some change freeze template. What are the exception to be captured etc. Appreciate all help
User avatar
Sonya03
Newbie
Newbie
Posts: 1
Joined: Wed Apr 05, 2017 8:00 pm

Thu Apr 06, 2017 1:38 am

UKVIKING wrote:A Change Freeze usually means no Changes except under extremely rigorous conditions

You as the new CM needs to define this first

And then distribute to all stakeholders and change raisers to concur

And then once agreed manage it like it is the reason for being

Only those that meet the transfers paris airports conditions get processed

Report to mgmt.
Report to stakeholder

Vulgar: This is where CM separates the sheep from the goats and the wolf.

You are the wolf. You have senior mgmt to override you in accordance with defined process above otherwise.. you become a goat or sheep and are useless as a CM - no authority just a ticket punch checker
Hello, thank you for you explicattion :)