CAB Conditional Approval

Discuss and debate ITIL Change Management issues
Post Reply
User avatar
reachjake
Newbie
Newbie
Posts: 1
Joined: Sun Sep 03, 2017 8:00 pm

Mon Sep 04, 2017 8:35 pm

If a Change Request is presented at CAB and there is action that needs to be complete before Approval can be granted, can conditional approval be granted?

Otherwise an Emergency Change would be needed if a major Change is to be implemented before before the following CAB.

For example, a Major Change Request is presented at CAB, however there are 2 UAT test cases remaining to be completed. Can this be Conditionally Approved based on the remaining UAT test completion. Or must it be Rejected and an Emergency change created if it is to be implemented before the next CAB?

Thank you.


User avatar
UKVIKING
ITIL Expert
ITIL Expert
Posts: 3639
Joined: Fri Sep 15, 2006 8:00 pm
Location: London, UK

Tue Sep 05, 2017 12:47 pm

It depends

It depends on the policy of the CM process

Some would require all testing to be completed before bringing the change to the CAB

Some would allow critical changes to fix an oiperation issue - high priority -level 1 - to be brought to the CAB whilst solution testing is still going on

if the CM policy allows that then yes conditional approval could be used
John Hardesty
ITSM Manager's Certificate (Red Badge)

Change Management is POWER & CONTROL. /....evil laughter
User avatar
Hoverhead
Itiler
Itiler
Posts: 10
Joined: Mon Nov 28, 2016 7:00 pm

Wed Sep 13, 2017 10:21 am

Agreed, I tend to conditionally approved changes if CAB are happy with the details technically. It could be waiting on things like customer approval etc..